2022

February 16, 2022

Concept Development Public Information Center

Feb

March 2022

Concept Development Complete

Mar

August 2022

Preliminary Engineering Initiated

Aug
2023

Spring 2023

Project website launch

May
2024

Winter 2024

Preliminary Engineering Public Information Center

Jan

Winter 2024

Obtain Environmental Clearances

Jan

Summer 2024

Preliminary Engineering Complete

Apr

Fall 2024

Final Design Initiated

Sep

TBD

Construction